September 4, 2026
This project is now substantially complete. The contractor is still responsible for re-establishing the disturbed boulevard grass. City staff has been compiling a punch list of small items that still need to be completed. This work is anticipated to occur over the next several weeks.
August 5
The contractor has moved milling of the TH 47 frontage road (Hall-Anderson Acres) to the week of August 10. The new pavement is proposed to be placed following milling and patching activities.
July 31, 2026
The contractor completed work in the Section 16 neighborhood and will remove all remaining signage and erosion control materials on Friday, July 31.
In addition, the contractor has finished paving in the Alpine Woods and Evergreen Point Townhouse neighborhoods. They are scheduled to seed and mulch these areas on Monday, August 3.
Later in the week of August 3, the contractor plans to mill the TH 47 Frontage Road (Hall-Anderson Acres). New pavement is expected to be installed during the week of August 10.
July 17, 2026
Restoration is scheduled for the Evergreen Point neighborhood. Pedestrian ramps have been completed. Milling is scheduled for the Alpine Woods, Evergreen Point and Hall-Anderson neighborhoods for Wednesday-Thursday next week.
July 6, 2026
The contractor is scheduled to place the new pavement in the Section 16 neighborhood on Tuesday, July 7, weather permitting. Please park all vehicles in your driveway and give the trucks, paver, and rollers plenty of space to complete their work. Once the rollers have finished, you may drive on the pavement. This generally takes 15 to 20 minutes after the paver places the material.
The contractor is also proposing to work on pedestrian ramp replacements and removals in the Alpine Woods neighborhood later this week.
June 26, 2026
This work has been pushed approximately one week. The contractor is now proposing to mill pavement within the Section 16 neighborhood on Wednesday, July 1. Removals and pedestrian ramp replacements are now proposed to begin during the week of July 6.
June 22, 2026
On Thursday, June 18, the city held a pre-construction meeting with North Valley, Inc., the contractor performing the improvements. Work is scheduled to begin in earnest on Wednesday, June 24, weather permitting. Read the fourth project update letter with the schedule.
View the construction map (PDF).