April 24, 2025
A proposal for geotechnical services and topographic surveys was awarded to Bolton & Menk, Inc. for the Carol-Rose Acres & Sports Haven developments. A letter was mailed to the residents who will be affected by this work.
This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies. See the Privacy Policy.
A proposal for geotechnical services and topographic surveys was awarded to Bolton & Menk, Inc. for the Carol-Rose Acres & Sports Haven developments. A letter was mailed to the residents who will be affected by this work.
On Tuesday, June 30, the city held a pre-construction meeting with North Valley, Inc., the contractor performing the improvements. Work is currently proposed to begin the week of July 20. A letter was sent to residents with more detailed information on the schedule. Read the fifth update letter.
On June 23, the Ramsey City Council awarded a construction contract to North Valley, Inc. for this project. A letter was mailed to the affected property owners. Read the fourth letter update.
The City has scheduled a pre-construction meeting with the contractor for Tuesday, June 30. More information, including a detailed schedule, will be available following the meeting.
On May 12, 2026, the City Council approved the final plans and specifications and authorized city staff to advertise for bids. Read the third update letter.
Please note that the public open house is scheduled for Thursday, November 13, at 5:30 p.m. This will be held at City Hall in the Alexander Ramsey Room.
A public open house will be held at City Hall for those affected by the upcoming project. Read the second update letter.
The contractor placed the final lift of new pavement on Wednesday, September 3. Restoration activities are currently scheduled to begin the week of September 14.
The Contractor is scheduled to place the final lift of new pavement on Tuesday, September 2, weather-dependent. Please park all vehicles in your driveway and give the trucks, paver, and rollers plenty of space to complete their work. Although you can drive on the pavement after the rolling process is complete, please avoid sharp turns on the fresh pavement.
Beginning next week, the Contractor is scheduled to begin restoration activities, including irrigation repairs, backfilling the disturbed boulevard areas with topsoil, hydroseed using a residential turf seed mix, repairing damaged landscaping, and resetting mailboxes. Restoration is anticipated to take 2 to 3 weeks to complete once it begins.
The contractor is currently scheduled to place the first lift of new pavement on Friday, August 7, weather-dependent. Please park all vehicles in your driveway and give trucks, the paver, and rollers plenty of space to complete their work. Once the rollers have finished, you may drive on the pavement. This generally takes 15-20 minutes after the paver places the material.
Weather-dependent, the contractor will finish hauling gravel on Friday, July 31.
During the week of August 3, the contractor is proposed to tolerance gravel and, later in the week, place the first lift of new pavement.
The contractor will reclaim (grind up) the existing pavement and aggregate base on Thursday and Friday of this week, July 23-24. Following reclamation, the contractor will compact the material, and the surface will feel similar to driving on a gravel road. Please be aware that there may be localized delays of several minutes as the equipment moves past driveways and adjacent streets.
This week, the mailboxes have been moved to accommodate the upcoming project. The week of July 20, erosion control will be set up. Pipework will take place on Monday, causing temporary road closures.
General Project Questions
Stacie Damjanovich
Engineering Administrative Assistant
Email Stacie
763-433-9895
Joe Feriancek
Assistant City Engineer
Email Joe F.
Sign up to our Newsletter
Stay up to date on the city's activities, events, programs and operations by subscribing to our eNewsletters.